Hohe Salve Bahn I: 2-seater chairlift will be replaced to an 8-seater gondola: 2.120 m length, height difference: 548,5m, carriage capacity: 2000 pers/h

The cost of construction has been estimated at 6 million euros. The length of construction only three months. The new route will be re-situated by 100 metres. Its starting point will be that of the existing chairlift. In addition to this investment the descent to the bottom of the valley will be improved.

Ellmau-Going: 
102 Sonnschwendtlift: a 4er chairlift  861m long will replace the former t-bar, lift capacity: 2.207 Pers./h 

 

Söll:                 
45 a 6-seater chairlift will replace the former t-bar – length 1.236m,  lift capacity: 3.000 Pers./