Features
1. First of its kind in the State.
2. Connecting the tourism destinations of Kailasagiri hill and Simhachalam
hills.
3. Total probable outlay : Rs. 2.00 crores.
4. Proposed to be taken on a BOT basis.
|

|
|

|
|
With a view to promoting tourism, it is proposed to
establish a Rope way from Kailasa Hill to Simhachalam hill
range across the NH 5 so that pilgrims coming to Simhachalam
Temple can visit the beach via Kailasa Hill. A
religious-cum-recreational circuit is thus proposed to be
created. A proper scientific study has to be conducted
initially, to establish the Ropeway. The Government land
available on the Simhachalam hill top has to be alienated by
the concerned authority before implementing the proposal. The
work on the feasibility study can start as soon as the lands
are alienated and handed over in advance to VUDA.
|
|
ROPEWAY CONNECTING SIMHACHALAM HILL AND KAILASAGIRI HILL AT NH 5 AND
PROVIDING HILL TOP ROAD FROM SIMHACHALAM DEVASTANAM TO VENKOJIPALEM.
Highlights
|
1. Project being formulated to exploit the tourism potential of
Kailasagiri and pilgrim traffic of Simhachalam.
2. Visage of Hill Top road from Simhachalam Devastanam to NH 5 (Venkojipalem),
for which survey and road alignment was completed by VUDA.
3. Total length of road 12.80 kms. at an estimated cost of 6.5
crores.
4. Erection of a ropeway connecting proposed Hill Top road and
Kailasagiri at NH 5 in BOT Basis.
5. Development of parks and view points atop the Simhachalam Hill
all along the Hill Top road at a later phase.
6. Comprehensive project proposal being submitted to the State
Govt. for clearance.
|
4. Road from Simhachalam Devastanam to NH 5 and also connecting the
NH 5 at Venkojipalem to Kailasa hill top.
|

|
|
The VUDA conducted a reconnoitre survey of Simhachalam Hill
starting from Simhachalam Hill to Hanumanthawaka i.e., upto N.H 5,
joining at Kailasa Hill. There is a feasibility to form a 40 ' wide
road from Simhachalam temple to NH 5. The total length of the road
from Simhachalam temple to the hilltop touching NH 5 is 11.30 kms.
The estimated road formation cost would be Rs.5.72 crores. From
Kailasa hilltop to N.H.5 at Venkojipalem, the length of road would
be 1.5 kms. The formation cost is estimated to be Rs.76 lakhs. The
above estimates include cross drainage works, protection works,
including tender variation rates. The above works can be taken up in
co-ordination with the VMC and R&B Department and Simhachalam
devasthanam.
|
Estimate 6.5 crores (Road Portion)
2.0 crores (Ropeway)
|