Skyrail Cairns Rainforest Cableway Upgrade Project Reaches Major Milestone

Stage 1 of the $85 million privately funded Skyrail Rainforest Cableway Upgrade Project is now complete, delivering a brand new cableway between Smithfield and Red Peak.

Spacious new, world-class 6-seat gondola cabins feature step-free boarding, panoramic floor-to-ceiling windows and enhanced accessibility.

The new cableway opens and full normal operations commence Wednesday 04 November 2026, connecting the new Doppelmayr system with the original experience. 

Stage 2 works to replace the Kuranda to Red Peak Line commence in 2027

Skyrail Cairns Rainforest Cableway has revealed its new panoramic gondolas with floor-to-ceiling windows allowing visitors even more immersive rainforest views when full operations from Smithfield to Kuranda resume on November 4.

The state-of-the-art new gondolas have been designed with ultimate passenger comfort, expansive views, and inclusivity in mind. They feature:
- Improved space and comfort
- Step-free floor-level boarding and wider entry doors
- Panoramic floor-to-ceiling windows for more immersive rainforest views

Skyrail Chairman, Ken Chapman said  “It is an exciting milestone to see the first of our brand-new gondolas launch on the rebuilt state of the art Smithfield to Red Peak cableway line.  These new and improved cabins are more spacious with improved comfort, panoramic windows and step free boarding to elevate the guest experience and make the World Heritage-listed rainforest more accessible and immersive than ever before.”

“We are recommencing full normal operations on November 4, and are thrilled to offer guests the unique opportunity to experience this exciting transition period;  gliding along our whisper-quiet new Doppelmayr system on the Smithfield line, while blending the original Skyrail experience on the journey to Kuranda.”
“The Kuranda to Red peak cableway line and gondolas will be replaced at the same time next year” he said.

Fast Facts:
- The cableway was closed for the upgrade from July 2026 with a Kuranda to Barron Falls loop experience operating while works continued on the Smithfield to Red Peak line.
- Wednesday 04 November 2026: Normal operations recommence with new cableway line.
- Looking Ahead: Works continue behind the scenes into 2027, with Stage 2 major works commencing from July 2027 to upgrade the Red Peak to Kuranda line.

For more information and project updates, visit: https://skyrail.com.au/upgrade/