ORDA to Spend $38 Million on Lifts in ’23

Citing a tight supply chain and manufacturer consolidation, the staff of New York’s Olympic Regional Development Authority requested board approval for seven major lift projects to be completed in 2023. Three state-run ski areas – Belleayre, Gore Mountain and Whiteface – each would receive new and upgraded lifts under the ambitious plan.

At Gore Mountain, bids are already in for replacing the Hudson triple with an extended detachable quad. The lowest bid came in at $8,761,520, though ORDA has not yet released the name of the winning manufacturer. This lift would operate year round and be accompanied by a new lodge. ORDA now also wants to replace Gore’s Bear Cub Poma in 2023. A replacement fixed grip chairlift would cost an estimated $3.5 million.

Four lift capital projects are proposed for Belleayre, the largest of which is a full replacement of Lift 7. A $6.5 million detachable quad would follow a modified alignment beginning near the top of the Lightning Quad. The Belleayre Express, a 16 year old detachable quad, would receive new operator houses and electrical systems at a cost of $1.7 million. Lift 8 is in line for a $400,000 upgrade and a new conveyor would round out $9+ million worth of lift projects at Belleayre.

The largest single project is at Whiteface, the largest vertical ski resort in the east. ORDA plans to build a two stage detachable quad from the Bear Den base area to mid mountain with an angle station along the way. This lift would cost a whopping $16.5 million due to the complex nature of the alignment.

The ORDA Board nearly unanimously approved resolutions for all projects to proceed as quickly as possible.

Article by Peter Landsman